The most fundamental calculation in the COCOMO model is the use of the Effort Equation to estimate the number of Person-Months required to develop a project. Most of the other COCOMO results, including the estimates for Requirements and Maintenance, are derived from this quantity.


Basic COCOMO

Basic COCOMO computes software development effort (and cost) as a function of program size. Program size is expressed in estimated thousands of source lines of code (SLOC)

COCOMO applies to three classes of software projects:

The basic COCOMO equations take the form

Effort Applied (E) = ab(KLOC)bb [man-months]

Development Time (D) = cb(Effort Applied)db [months]

People required (P) = Effort Applied / Development Time [count]

where, KLOC is the estimated number of delivered lines (expressed in thousands ) of code for project. The coefficients abbbcb and db are given in the following table:

Software projectabbbcbdb
Organic2.41.052.50.38
Semi-detached3.01.122.50.35
Embedded3.61.202.50.32

Basic COCOMO is good for quick estimate of software costs.

Intermediate COCOMO

Intermediate COCOMO computes software development effort as function of program size and a set of “cost drivers” that include subjective assessment of product, hardware, personnel and project attributes. This extension considers a set of four “cost drivers”, each with a number of subsidiary attributes:-

Detailed COCOMO

Detailed COCOMO incorporates all characteristics of the intermediate version with an assessment of the cost driver’s impact on each step (analysis, design, etc.) of the software engineering process.

The detailed model uses different effort multipliers for each cost driver attribute. These Phase Sensitive effort multipliers are each to determine the amount of effort required to complete each phase.

In detailed COCOMO, the effort is calculated as function of program size and a set of cost drivers given according to each phase of software life cycle.

A Detailed project schedule is never static.

The five phases of detailed COCOMO are:-

Line Of Code

 Function Point